Simulation: a fictional property for practice.
A $90,000 lot to build and sell a new house
New 2,000 sq ft homes nearby sell for about $520,000. Is there room for profit after building costs?
A fictional lot inside a city, with a construction loan. Building costs, fees and rates are example assumptions.
- Lot price: $90,000
- Plan: Build a 2,000 sq ft house and sell it
- Nearby new homes: About $520,000
- Build cost (example): $150 a square foot, $300,000
Mission 1: Can you build what you plan?
Pick all you’d check before buying.
- Zoning, setbacks and height limits, with the city’s planning department
- HOA rules or recorded restrictions (CC&Rs) on design and size
- Water, sewer and power at the street, and the connection and impact fees
- Soil, slope and drainage
- Nothing: a lot inside a city is always buildable
Confirm what you can build and what it costs to connect before you buy the lot.
Mission 2: Every cost
- Lot and buying costs (2%): $91,800
- Construction: $300,000
- Plans, permits, impact and connection fees (example): $35,000
- Construction loan interest and fees (example): $25,000
- Selling costs (7% of $520,000): $36,400
- Total cost: $488,200
- Profit before taxes: About $31,800, about 6% of the sale price
A 10% rise in construction costs ($30,000) would erase almost all of it.
At $90,000, what do you do?
Buy, investigate or pass? Work through the drill to see what an experienced investor would weigh.